| NevadaAll construction | Every construction site in Nevada, public or private (NDOT work and upkeep on occupied property excepted). | Workers: OSHA 10 Construction, within 15 days of hireSupervisors: OSHA 30 Construction, within 15 days of hireCards no longer expire (SB 233 of 2015 removed the old 5-year limit). | NRS 618.983 and 618.987 |
| New York City, NYAll construction | Construction and demolition sites in the five boroughs that need a Construction Superintendent, Site Safety Coordinator or Site Safety Manager (not minor alterations or a new 1-3 family home). | Workers: SST Worker card (40 hours), before working on the siteSupervisors: SST Supervisor card (62 hours), before serving in the roleSST cards last 5 years. Renew with an 8-hour refresher (supervisors 16) taken in the 12 months before. | NYC Building Code § 3321 (Local Law 196 of 2017) |
| Philadelphia, PAAll construction | Every worker on permit-regulated construction or demolition work in Philadelphia; licensed contractors need at least one OSHA 30 supervisor. | Workers: OSHA 10 Construction, before working; carry the card at all timesSupervisors: OSHA 30 Construction, with the contractor license application or renewal (within 5 years)Licensed contractors show an OSHA 30 from the last 5 years (or 30 hours of continuing education) at each license renewal. | Philadelphia Administrative Code § A-1001.4 and § A-1001.5 |
| ConnecticutPublic projects | State or municipal projects: new construction of $1,000,000 or more, or remodeling, repair or alteration of $100,000 or more. | Workers: OSHA 10 Construction, proof with the first weekly certified payrollThe card must be dated within 5 years of the project start; plumbers and electricians with older cards need a 4-hour refresher. | C.G.S. § 31-53b |
| Miami-Dade County, FLPublic projects | County-funded public buildings or public works over $1,000,000, and some private projects over $1,000,000 on County land. | Workers: OSHA 10 Construction (OSHA 30 also accepted), before working on the projectNo renewal stated. | Miami-Dade Code § 2-11.17; Implementing Order 3-61 |
| MainePublic projects | State-funded public works with a contract of $50,000 or more, for craft workers covered by prevailing wage. | Workers: OSHA 10 Construction, while on the work siteNo renewal in the statute. | 26 M.R.S. § 1317 |
| MassachusettsPublic projects | Public works and public building contracts over $10,000 (state, counties, cities, towns, housing authorities). | Workers: OSHA 10 Construction, by the first day on the worksiteNo renewal in the statute. | M.G.L. c. 30 § 39S |
| MissouriPublic projects | All public works projects (no dollar threshold), for on-site workers of contractors and subcontractors. | Workers: OSHA 10 Construction, within 60 days of starting on the projectNo renewal in the statute. | RSMo § 292.675 |
| New HampshirePublic projects | Public works for a state agency or municipality, or paid partly with state funds, of $100,000 or more. | Workers: OSHA 10 Construction, before starting workNo renewal in the statute. | RSA 277:5-a |
| New YorkPublic projects | Contracts where the state or a municipality is a party and the total cost is $250,000 or more (prevailing-wage workers). | Workers: OSHA 10 Construction, before doing any work on the projectNY DOL says completion cards do not expire for this law. | N.Y. Labor Law § 220-h |
| Rhode IslandPublic projects | Municipal and state construction projects with a total cost of $100,000 or more. | Workers: OSHA 10 Construction, card on you at all times while workingNo renewal in the statute. | R.I. Gen. Laws § 37-23-1 |
| West VirginiaPublic projects | Public improvement contracts over $50,000 (people on site fewer than 21 days excepted). | Workers: OSHA 10 Construction, within 21 days of being assigned to the siteNo renewal in the statute. | W. Va. Code § 21-3-22 |
| Boston, MASite safety coordinator | Projects over 50,000 sq ft and demolition of buildings 4 stories or taller must name a site safety coordinator. | Supervisors: OSHA 30, named to Inspectional Services before work startsNo renewal in the ordinance. | Boston City Code § 16-64.6 |
| Somerville, MASite safety coordinator | Construction and demolition projects whose permit needs a site safety plan must name a site safety coordinator. | Supervisors: OSHA 10, certificate to Inspectional Services before the permit is issuedNo renewal in the ordinance. | Somerville Code ch. 8, §§ 8-375 to 8-381 |
| NevadaCertain industries | Workers whose main job is on a theater, sound stage, showroom, arena or film/TV site (rigging, scenery, props, audio, lighting, camera). | Workers: OSHA 10 General Industry, within 15 days of starting on a siteSupervisors: OSHA 30 General Industry, within 15 days of starting on a siteExpires after 5 years: retake the course or log 5 hours (supervisors 15) of continuing education. | NRS 618.9911 |
| NevadaCertain industries | Workers whose main job is trade-show and convention setup (booths, displays, rigging, loading, temporary power). | Workers: OSHA 10 Construction or General Industry, within 15 days of hireSupervisors: OSHA 30 Construction or General Industry, within 15 days of hireExpires after 5 years: retake the course or log 5 hours (supervisors 15) of continuing education. | NRS 618.9929 and 618.9930 |
| NevadaCertain industries | Employees of a licensed cannabis establishment; the establishment pays for the course. | Workers: OSHA 10 General Industry, within 1 year of hireSupervisors: OSHA 30 General Industry, within 1 year of hireNo renewal in the statute. | NRS 618.9948 |
| FloridaWorkers under 18 | Workers aged 16 or 17 on residential building construction, and the adult directly supervising them. | Workers: OSHA 10, before being employed on residential constructionNo renewal stated. | Fla. Stat. § 450.061(2)(b) |